1. Design phase
Duration: 3-4 weeks (depending on the client’s availability and the clear information he/she can provide).
- Initial meeting with the client (1-2 days): Understanding the client’s needs and desires.
- Preliminary design development (2 weeks): Creation of preliminary sketches and models.
- Design review and adjustments (1 week): Adjustments based on client feedback.
2. Acceptance phase
Duration: 1-2 weeks
Activities:
- Final design presentation (1 week): Show the client the final design with specific details.
- Client approval (1 week): Time for client to review and approve the design.
- Final measurement at client’s home.
3. Manufacturing phase
Duration: 8-12 weeks (depending on the material chosen)
Activities:
- Furniture production (7 weeks): Manufacture of kitchen furniture according to the approved design.
- Quality check and preparation (1 week): Ensure all components are ready for installation.
4. Installation phase
Duration: 1-2 weeks
Activities:
- Site preparation (1-2 days): Prepare space for installation, transport of furniture.
- Furniture and appliance installation (1-2 days): Assembly and installation of furniture and appliances.
- Final check and adjustments (2-3 days): Making sure everything is perfect and making any necessary adjustments.
- Installing the worktop: (10-15 days) Depending on the material. Installation at the client’s home, 1 day.
5. Completion phase
Duration: 1 week
Activities:
- Meeting with the client to go over all the details.
- Delivery of final invoice, the guarantee of your kitchen.
Times may vary if:
- Holidays such as Christmas or August.
- If the work is delayed due to external circumstances.
- If the proposed design does not fit and we need to design more options.
- Etc.